Updates on sidewalk construction projects on SW 11th, SW Multnomah, SW Illinois, SW Huber, SW Sunset, SW Spring Garden, SW Maplewood
SW 11th Ave: Gaines – Gibbs
Andrew Aebi, Project Manager, 503-823-5648
All sidewalk work and street reconstruction work is complete, and the street has been reopened to frequent service bus and regular traffic. Tree planting and construction punch list items pending.
SW Multnomah: 22nd – 40th Ave
Richard Newlands, Project Manager, 503-823-7780
Because of high bids on other projects we recently advertised, we have determined that we will likely receive lower bids on this project if we delay bidding until September with construction scheduled for January 2014.
SW Illinois / Vermont Neighborhood Greenway
Kyle Chisek, Project Manager, 503-823-7041
As with the Multnomah project, we are delaying bidding until September.
SW Huber St: 37th – 43rd Ave
Chris Armes, Project Manager, 503-823-7051
Notice to Proceed was issued August 2, 2013. On site work has not started.
SW Sunset: DeWitt – 18th Dr
Chris Armes, Project Manager, 503-823-7051
The majority of civil work along the west side is complete. The contractor has shifted to the underground sewer work and the west side of the roadway. Work is progressing on schedule and should be complete by September 21st.
SW Spring Garden / 19th / 22nd Ave
Chris Armes, Project Manager, 503-823-7051
Construction started August 5th and should be complete the end of October. The contractor started work at the intersection of 17th / SW Spring Garden and is moving toward SW Taylors Ferry Road. Neighborhood residents have been notified of the work and will be notified again once work will occur directly in front of their home.
Maplewood Road needs to have the speed bumps extended onto the shoulder. PBOT is not going to put a center strip down.